Rail2026
Botley Road Interchange
Rail infrastructure project in Oxford
Platform works and station access improvements, built across eighteen months of night possessions beside a live railway.
New build services
Project facts
- Client
- Named on request
- Location
- Botley Road, Oxford
- Contract type
- Traditional, NEC3
- Contract value
- £4.2m
- Night possessions
- 38
- Programme
- 78 weeks
- Completed
- March 2026
01 — The brief
Eighteen months of night work
The station needed a lengthened platform, a new accessible ramp and rebuilt canopy supports, all within a live operational railway carrying passenger services until late evening and freight overnight.
Every hour of work had to fit inside a booked possession, and anything left incomplete at 5am had to be made safe for a 6am service. There was no room for a programme that assumed continuous access.
02 — Delivery
Planned to the possession, not the week
The programme was written backwards from 38 booked possessions, each between four and six hours. Every possession had its own method statement, plant list and demobilisation plan, and work that could be prefabricated off site was — including the ramp balustrades and the canopy support brackets.
Our site manager held the possession log and the safe work pack for every shift, and one of the directors attended the first possession of each new work type. Two possessions were handed back early; none overran.
- 38 booked night possessions
- Method statement per possession
- Off-site prefabrication of balustrades and brackets
- Made safe for 6am service every shift
- Platform lengthened by 46m
- New accessible ramp and canopy supports
03 — The outcome
No overruns, no service impact
FF Construction completed the £4.2m Botley Road Interchange platform and access works in March 2026, across 38 night possessions over 78 weeks, without a single possession overrun or daytime service disruption.
The platform was lengthened by 46m and the station became step-free for the first time. The work was delivered with no RIDDOR-reportable incidents.
Gallery
Work that only happened at night

A typical possession: four hours from handover to hand back. 
Balustrades were built off site and craned in during a single shift. 
The finished ramp made the station step-free for the first time.
Related projects
Other infrastructure and new build work
All projects
Commercial2025
Osney Mead Innovation Quarter
Laboratory and office building for a science park operator, taken on a two-stage design and build contract.
- Area
- 4,600 m²
- Value
- £5.4m
- Location
- Oxford

Healthcare2025
Summertown Medical Centre
Full refurbishment of a working GP surgery, phased across nine consulting rooms without closing the practice.
- Value
- £980k
- Programme
- 22 weeks
- Location
- Summertown

Industrial2024
Headington Quarry Warehouse
Steel-framed distribution unit with 12m clear internal height, a fitted first-floor office and a 40-space yard.
- Area
- 2,800 m²
- Value
- £3.1m
- Location
- Headington
Start a project
Work beside a
live operation?
Constrained access, possessions and out-of-hours working are most of what we do. Tell us the constraints and we will plan them properly.
Or call 01865 000 000, Monday to Friday, 7am to 5pm.